Engineering Services for the Three-year Shutdown Provided for in 2022 (Turnaround Engineering)
Groupement Touat Gaz (GTG) assigned Velosi to prepare and plan triennial and decennial shutdowns as well as develop and deliver all deliverable documents to GTG based on the work and equipment inspection lists.
The main objective of the project is to update the technical data of equipment in the company network and to establish Inspection Plans (IPs), Inspection Routines (IRs), Equipment Bill of Materials (BOMs), Materials Requirements Planning (MRP), Dossier of Planned work at every equipment, List of works at Every Maintenance discipline, List of purchase orders for services or special tools, Planning for all the works included in the shutdown, Procedures for works in confined spaces and Final Shutdown execution phase for the Triennial and Decennial Shutdown.
Velosi will provide the following Deliverables:
- Inspection plans (IPs) accordingly to Algerian law.
- Inspection routines (IRs).
- Equipment Bill of Materials (BOMs).
- Materials Requirements Planning (MRP).
- Dossiers of the planned works at every piece of equipment (one dossier by equipment).
- Dossier of inspection program for the shutdown.
- Dossiers for works with special requirements as the following ones:
- Scaffolds,
- Hot works & Radiographs.
- Mechanical isolation, Electrical isolation & Maintenance Override Switch (MOS).
- Works in confined spaces.
- PSV´s to be inspected and tested.
- Works with cranes or vehicles & Lifting operations
- Simultaneous operations (SIMOPS).
- Lists of purchase orders for services or special tools.
- Dossier with planning for all the works included in the shutdown.
- Dossier of consignation / de consignation procedure.