Preparation of Standard Operating Procedures (SOPS) for OTTCO regarding the Package-C Project
Scope
The Project Scope of work includes the development of the following SOPs:
1 | Procedure for Crude Storage Tank Line-Up/ Filling including Checklists For Inspection Of Nominated Tanks Before Start |
2 | Procedure for Crude Storage Tank Shutdown & Handover to Maintenance |
3 | Crude Storage Tanks Measurement, Sampling and Gauging Procedure |
4 | Crude Storage Tank Overflow Emergency Procedure |
5 | Procedure for Start-up After ESD due to Failure of Power |
6 | Total Plant (Facility) Shutdown Procedure |
7 | Procedure for Evaporation Pound Filling |
8 | Procedure for Export Pump Shutdown and Handover to Maintenance |
9 | Procedure for De-watering Pump Handover to Maintenance |
10 | Procedure for Crude Tank Stripping Pumps Shutdown and Handover to Maintenance |
Process
Accordingly, Velosi developed an operating procedure flow chart including all the process activities. After the development procedure follows QA/QC interdisciplinary check with submission and review of the operating procedures and review workshop of OP’s. The process accounted for two drafts version of the OPs to the company.
Outcome
Velosi successfully developed the required SOPs as per COMPANY requirements.
Deliverables
Velosi submitted the following deliverables:
- Procedure for Crude Storage Tank Line-Up/ Filling including Checklists For Inspection Of Nominated Tanks Before Start
- Procedure for Crude Storage Tank Shutdown & Handover to Maintenance
- Crude Storage Tanks Measurement, Sampling, and Gauging Procedure
- Crude Storage Tank Overflow Emergency Procedure
- Procedure for Start-up After ESD due to Failure of Power
- Total Plant (Facility) Shutdown Procedure
- Procedure for Evaporation Pound Filling
- Procedure for Export Pump Shutdown and Handover to Maintenance
- Procedure for De-watering Pump Handover to Maintenance
- Procedure for Crude Tank Stripping Pumps Shutdown and Handover to Maintenance