THIRD PARTY INSPECTION DURING FABRICATION OF NORTH LINK BRIDGE AT IKAN ENGINEERING SERVICES (PVT) LIMITED LAHORE FOR SAMBU

Velosi was hired by Hannover Consulting Engineers to perform design review of NG pipe network for construction of a building at Sector RBW-7, Plot C25, Al-Raha Beach, Abu Dhabi.
Objective
SAMBU has been awarded Lowari Tunnel Project by National Highway Authority Pakistan. SAMBU Placed order to IKAN Engineering for Steel Structure Fabrication Work. Steel Structure for North Link Bridge was Fabricated & Installed by IKAN Engineering and Velosi Pakistan performed Third Party Inspection during all Fabrication activities. The objective of this contract was:
- Visual Inspection of Fit-up & Welding
- UFD, MPI & DPT of Welding Joints
- To provide Technical Assistance as per Client Requirement
Scope of Work
Applus + Velosi intend to carry out the services for third party inspection of fabrication of steel structure at IKAN Engineering Serviced (Pvt) Limited premises. The scope is third party inspection.
Inspection Activities
- Material Inspection
- Plate Marking & Cutting Stage
- Fit-up Inspection
- Welding Visual Inspection
- NDT Inspection
- Final Dimensional Inspection
- Surface Preparation & Paint
Deliverables
- Inspection Reports