NDT INSPECTION ON HIGH PRESSURE PIPELINE DOWNSTREAM OF COMPRESSOR STATIONS

  • Sui Northern Gas Pipeline Limited (SNGPL)
  • Fasialabad, Pakistan
  • South Asia
NDTStations
Velosi was hired by Hannover Consulting Engineers to perform design review of NG pipe network for construction of a building at Sector RBW-7, Plot C25, Al-Raha Beach, Abu Dhabi.

Objective

To carry out the following NDT techniques on following segments of Pipeline operated by SNGPL in Faisalabad Region

  • 18” Dia Main Line, AC-7 / AV-38
  • 24” Dia Main Line, AC-7 / AV-38
  • 16” Dia Loop Line, A-11 / BV-3
  • 16” Dia Loop Line, A-11 / CV-4
  • 16” Dia Loop Line, BC-1 / B-2

Scope of Work

The corrosion department of SNGPL proposed to assess the integrity status of its pipelines segments downstream of compressor stations by utilizing the following NDT Techniques:

  • Ultrasonic Thickness (UT) Gauging along with Corrosion Mapping for internal corrosion loss
  • Magnetic Particle Inspection (MPI) for Stress Corrosion Cracking (SCC)
  • In-Situ Metallographic Testing at selected points

Deliverables

VISP provided a comprehensive report at completion of project with three hard copies along with one electronic copy of reports. The final report included the following deliverables:

  • Inspection findings: defects and deviations
  • Remedial actions to be undertaken for the redress of the same and guidelines to improve the ICCP monitoring and maintenance
how can we help you?

Contact us at the Velosi office nearest to you or submit a business inquiry online.

The strength of our approach comes from offering a multiregional service while meeting local needs. Velosi achieves this because we operate in selected world’s major established and emerging markets.

Mr. Ijaz Ul Karim Rao
Ijaz Ul Karim Rao
MD, Velosi Asset Integrity Limited

Let us help you to provide the best solution for your asset !